|
ICRI
PROJECT AWARDS
2005
|
 |
ICRI 2005
PROJECT AWARD WINNERS
|
AWARD OF EXCELLENCE:
Water Structures Category
JOHN DAY DAM NAVIGATION LOCK REPAIR

Rufus, Oregon
Submitted by
Pioneer
Waterproofing Company, Inc.
|
 |
The
John Day Dam was the last major dam building project competed
on the lower Columbia River. Construction began in 1958
and was completed in 1971. The Navigation Lock allows
commerce to pass up and downstream and is an important
part of the northwest’s economy moving millions
of tons of northwest’s agricultural and forest products
to be shipped through out the world.
In 2003, over 2500 cracks were discovered in two of the
sections of the Lock (called Monoliths), some as large
as 2 in. in width which ran the full height of the lock,
threatening the structural integrity of the Lock itself.
The possibility existed that portions of the Lock could
fail collapsing into the Lock, which could close all commercial
river traffic on the Columbia River for up to one year.
Had this had happened the economic impact on the northwest’s
economy would have been in the billions of dollars.
The scope of work on the project involved epoxy injection
of up to 2500 lineal ft of concrete cracks ranging in
width from 1/8 to 2 in. and varying in depth from 4 to
over 15 ft. Most of the cracks to be injected were up
to 150 ft in height.
The Lock was required to be shut down during the entire
epoxy injection portion of the project. Due to the economic
impact of the shut down, the work was required to be completed
in no more than 28 calendar days.
|
|
Owner
Army Corp of Engineers
Portland, Oregon
Project Engineer/ Designer
Army Corp of Engineers
Portland, Oregon
Repair Contractor
Pioneer Waterproofing Company, Inc.
Portland, Oregon
Material Supplier/ Manufacturers
ChemCo Systems, Inc.
Redwood City, California
DeNeef Construction Chemicals (US), Inc.
Houston, Texas
|
|